Grid2Shell
Bielefeld


Client Schüco International KG
Architecture Schüco International KG
Image credits Schüco International KG
Scope Structural design phase 4-5
Materials Steel, Glas
Area 66 m²
Length 9 m
Width 7 m
Height 6 m
Planning period 2022
Completion 2023

Initially a prototype for the BAU 2023 in Munich, now a permanent exhibit on the Schüco Campus in Bielefeld.

As part of BAU 2023, Schüco presented a structurally sophisticated Grid2Shell exhibit. After careful dismantling, the structure was put into storage with the aim of future reuse. In addition to the structural analysis carried out for the exhibition at BAU 2023, we also performed a new structural assessment under different conditions for its reinstallation on the Schüco Campus in Bielefeld. This allowed the existing structure to be sustainably repurposed and functionally integrated into its new surroundings.